I don't understand Set Estimated Progress action.
The value it takes says
Specify a numeric value that represents the total number of actions that will run this time.
The progress bar never reflects anything like an accurate guage - its wild and goes up and down with no apparent reason. My build is simple with few branches or conditionals. It would be better if I could just tell FB how much of a % is done at this point. My actions are very uneven in time they consume. Just because I have 200 actions, 20 of them may take 50% or more of the total build time. The other 180 actions may take the other 50%.