Unit tests failing and advancing to next stage

1. Continua version number and edition: 
v1.8.0.176 - 64 bits

2. Operating system for Continua and agents:
 
Windows 7 Professional Server 64 bits - Server and one agent.

3. Database platform:
 
Bundled PostgreSQL

4. How much CPU / RAM / Diskspace do you have free on the Continua server, agents, and database:  
90% free cpu, 58% free RAM (7gig), 14% free hard disk (104 gig)  

5. A detailed description of the issue: 
Sometimes a unit test fails and passes to the next stage without taking into account the “stage gates” requiring zero failed tests.

Failed unit test:
http://d.pr/i/12AIm

Stage gates:
http://d.pr/i/1iSRK

Configuration:
http://d.pr/i/BEMI

Diagnostics Report:
–removed for privacy—

This problem happens 2 out of 10 times and has been happening for the last 3 months.

Thanks in advance




Hi Luis,

Can you send a build log showing this happening to support@finalbuilder.com?  If you have a debug log this would be even better.