Hi !

I have a problem with the fields : filename and projectname when i create a log file (xml format) with include projects. Indeed, i have a global project which launch another projects :

Global Project.atp5
       Project 1.atp5
       Project 2.atp5
       Project 3.atp5

I dont understand why i have not the subproject name in variable Projectname. I have always the name of the global project. Is it normal ? I need to have the correct name for my logs system.



Pierrick

We’re looking into this, will post here when I have a fix.

Ok thank you …
Tell me if you need some more informations.

regards,

Hi

Thanks for your patience, this build should resolve this issue :

http://downloads.finalbuilder.com/downloads/automise/500/AT500_678.exe

Wonderfull ! it’s working. Thanks for your reactivity.
I was important because i use this field to log the statut of the task.

Regards,

Pierrick

Posted By Fougere on 14 Dec 2016 09:08 AM
Wonderfull ! it's working. Thanks for your reactivity.
It was important because i use this field to log the statut of the task.

Regards,

Pierrick


Hi !
First at all, happy new year for automise team !! :smiley:
Then, I have the same problem with the field : starttime (and runtime)
The starttime is always the start time of global project. So it’s not the good information for sub project log file.

Is it normal ? because it’s not easy calculate the correct runtime for each project.

Regard,

PF





Currently the build start time is when the outer project started. The best way to get an inner project start time is to look at the first action start time in the export log for that project. Would this work in your environment?

Indeed, i think we ll take this way. I ll discuss with our developpment team.

Thx.